After Rehabilitation

- After Rehabilitation
Owner: VR 1151
- Project Budget: $ 5 Million
- Completion Year: 2010
- Engineer: JRS Engineering Ltd.
- Project Architect and BEP: Terra Shimbashi
- The Challenge: A full building remediation for a 4 storey 57 unit wood frame building with exterior walkways, stairs and courtyard over parking, resulting in a major modernization and aesthetic upgrade, including enlarged window openings, roof overhangs, green membrane courtyard and a new ventilation design.
- Materials: Rainscreen Stucco, Aluminum windows, 2 ply SBS roofing at roofs and Terapro PMMA membrane at exterior walkways.